Harrström Wind Park, Vaasa, Finnland

  • Gebäudeart:
  • Energieversorgung
Vollbild Schließen

Peikko Group’s Finnish subsidiary Peikko Finland Oy delivers gravity foundations to the Harrström Wind Park in Korsnäs near Vaasa, Western Finland. The project consists of four wind turbines manufactured by Vestas.

The deliveries comprise Anchor Bolts, Anchor Cage, Headed studs, Steel formwork and foundation reinforcement. Peikko’s turn-key project delivery introduces foundation design with 3 meter extension for higher hub height, all foundation components, and installation including concreting. The deliveries and installation started in December 2016 and the foundations will be finished during spring 2017.

The Harrström wind park is developed by Harrström Vinpark AB. Vestas delivers 4 pcs of V90 3 MW turbines with hub heights of 100 meters. The turbines will be installed right after foundation are completed and the wind park will be operational before summer 2017.

Mehr lesen down-arrow.png

Projektdaten

Projektentwickler:
Harrström Vinpark AB
Lieferzeitraum:
2016-2017
Fertigstellung:
2017
Anzahl Windkraftanlagen:
4
Hersteller:
Vestas
Leistung (MW):
V90 3 MW
Turmhöhe (m):
100